List of steps
(Total number of steps: 5)
Obtain Building and Engineering Construction Inspection report/certificate  (5)

Preview & Print

Properties
 
Summary of the procedure
 

Where to go? (3)

You will have to go to the following agencies. The number indicates how many interactions are required with each entity.
Occupational safety and health authority (x 3)
1 4 5
Occupational safety and health authority
Customer's Site
2
Customer's Site
National Microfinance Bank (NMB)
3
National Microfinance Bank (NMB)

What you will get (1)

The objective of the procedure is to obtain those documents.
Building and Engineering Construction Inspection report/certificate
5

Required documents 

The documents with green band will be provided to you during the procedure.

OSHA site layout plan
1
OSHA site layout plan
NMB Bank Pay slip
3
NMB Bank Pay slip
NMB Bank Pay slip
4
NMB Bank Pay slip
OSHA Government Receipt
5
OSHA Government Receipt

How much?

Estimated cost of the procedure  TZS  400,000

change the values with the

Cost detail

Estimate your cost

80 % contract / transaction amount
- TZS 400,000
of registration fee is charged as inspection fee
500,000

How long ?

The estimated total time is calculated by adding the time spent: 1) waiting in queue, 2) at the counter and 3) between steps.
  Min. Max.
Total time (sum): 1 d 1 d
of which:
Waiting time in queue (sum): 0mn 25mn
Attention at counter: 5mn 20mn

Legal justification?

The regulations which justify the procedure and its content
OSHA General Administrative Rules 2015 OSHA General Administrative Rules 2015
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License